top of page

PROJECTS
we're proud of

100% Completion Rate on Projects Awarded

Playground Site Prep

Castle Rock Tiered Playground 
Billings Parks & Rec 2022

  • The new 100x140' playground was designed to have a tiered depth change throughout while still needing to provide ADA Accessibility. Site files were not available, which made the entire grade and footprint a field fit project.

  • Playground has an 18" depth difference on the interior to the final grade to allow for 1.5' of fall protection material.

  • An 8" thickened edge must accompany all new material to blockade material intermixing. 

  • 22" block rock was installed in an arch around different parts of the play pod in lieu of thickened edge.

  •  Irrigation, plants stone steps and nautical boundary stakes were the final addition to this brand new park.

Rainbow Point Boat Ramp

West Yellowstone
USFS 2020

  • Rainbow Point Boat Ramp was installed in April of 2020 under the USFS at Hebgen Lake near Big Sky Montana. 

  • The construction of the ramp required dewatering to allow a 48' long concrete armorflex pad to be laid on top of non-woven geotextile. 

  • A 3' by 70' thickened edge ramp was installed with a angle grooved surface finish to allow for water drainage into the riprap armored edge. 

  • A concrete apron was poured as well as parking lot grading and a handicap accessible parking pad with striping. 

Excavation

  • Grading of Gravel Parking Lots and Roadways.

  • Excavation under roadways and in waterways while being cognizant of wildlife and pollution hazards involved.

  • Embankment projects with Native and foreign material used.

Rainbow Point Boat Ramp

West Yellowstone USFS 2020

  • Rainbow Point Boat Ramp was installed in April of 2020 under the USFS at Hebgen Lake near Big Sky Montana. 

  • The construction of the ramp required dewatering to allow a 48' long concrete armorflex pad to be laid on top of non-woven geotextile. 

  • A 3' by 70' thickened edge ramp was installed with a angle grooved surface finish to allow for water drainage into the riprap armored edge. 

  • A concrete apron was poured as well as parking lot grading and a handicap accessible parking pad with striping. 

Shade Sail Installation

Lewis and Clark Interpretive Center
USFS 2020

  • Lewis & Clark Interpretive Center has an outdoor classroom above the historical Missouri River near Giant Springs in Great Falls MT. The Site needed shade for the lectures and gatherings hosted by the facility. 

  • The Construction of the Shade Sail required 4'x9' buried slabs reinforced with rebar to handle the large gale force known in Great Falls, MT. 

Cooney Reservoir Campsite Erosion Repair

Cooney Reservoir Campsite Erosion Repair
MT FWP 2020

  • Reservoir Campground had eroded campsites that sat directly at the waters edge. High waters had eroded the banks leaving steep and unsafe edges for campers. 

  • The project involved special borrow to be hauled in and embankment of camp site edges. Geotextile was laid below a concrete armor mattress called Flexamat. Over 60,000 SF of the erosion control product was installed on 13 radial banks. 

bottom of page